The equipment belonging to the boiler room meets the following requirements:

The equipment belonging to the boiler room meets the following requirements:

 

 

1) Oil or gas boiler rooms and transformer rooms should be located on the first floor or the basement near the outer wall, but constant (negative) pressure oil or gas boilers can be installed on the second floor or on the roof. The constant (negative) pressure gas boiler installed on the roof shall not be less than 6m away from the safety exit leading to the roof.

Boilers using combustible gas with a relative density (ratio of air density) not less than 0.75 as fuel shall not be installed underground or semi-underground.

2) The evacuation doors of the boiler room and transformer room should directly lead to the outdoors or safety exits.

3) The boiler room, transformer room, etc. and other parts should be separated by fire partition walls with a fire resistance rating of not less than 2.00h and non-combustible floor slabs with a fire resistance rating of 1.50h. There should be no openings in the partition walls and floor slabs, and Class A fire doors and windows should be used when doors and windows are indeed required on the partition walls.

4) When the oil storage room is installed in the boiler room, its total storage capacity should not be greater than 1m³, and the oil storage room should be separated from the boiler room by a fire partition wall with a fire resistance rating of not less than 3.00h; it is indeed necessary to install it on the fire partition wall For doors, Class A fire doors should be used.

5) Fire partition walls with a fire resistance rating of not less than 2.00h should be installed between the transformer rooms, between the transformer rooms and the power distribution room.

6) Oil-immersed transformers, multi-oil switch rooms, and high-voltage capacitor rooms should be equipped with facilities to prevent oil from being scattered. Accident oil storage facilities capable of storing the entire oil volume of the transformer should be installed below the oil-immersed transformer.

7) Fire alarm devices should be installed.

8) Fire extinguishing facilities suitable for the capacity of boilers, transformers, capacitors, and oil switches, etc. and the scale of the building should be installed. When other parts of the building are equipped with automatic sprinkler systems, automatic sprinkler systems should be installed.

 