1. The normal oil level is 1/2-3/4 of the oil window (can not exceed). When there is moisture in the vacuum pump or the color of the oil turns black, the new oil should be replaced at this time (generally once a month or two of continuous operation) , 1# vacuum gasoline or 30# gasoline, oil can also be used).
3. The impurity filter should be disassembled and washed frequently (usually once every 1-2 months, such as packaging debris, the cleaning time should be shortened).
4. After working continuously for 2-3 months, the back cover 30 should be opened to add lubricating oil to the sliding parts and switch bumps, and the connecting activities on the heating rod should be lubricated according to the usage conditions.
5. Regularly check the triple parts 24 of decompression, filtration and oil mist to ensure that there is oil (sewing machine oil) in the oil mist and oil cup, and there is no water in the filter cup.
6. The heating strip and the silicone strip should be kept clean, and no foreign matter should be stuck, so as not to affect the sealing quality.
7. On the heating rod, the second layer of paste under the heating sheet plays an insulating role. When it is damaged, it should be replaced in time to avoid short circuit.
8. The working air source and inflation air source are provided by the user. The working pressure of the vacuum packaging machine has been set to 0.3MPa, which is more appropriate. Do not adjust it too much unless there are special circumstances.
9. The vacuum packaging machine is not allowed to be tilted and impacted during the handling process, and it is not allowed to be tipped for handling.
10. The vacuum packaging machine must have a reliable grounding device during installation.
11. It is strictly forbidden to put your hand under the heating rod to prevent injury. In case of emergency, cut off the power immediately.
12. When working, first ventilate and then power on, and when shutting down, first power off and then cut off the gas.