Mold installation steps:

1. Make adequate preparations

Turn on the power, start the manual button of the injection molding machine, put the equipment in manual mode, click the oil pump button, and start the injection molding machine hydraulic system. After these operations are ready, prepare the sling and transport the mold to the location, and pay attention to ensure that the mold matches the product accessories.

2. Install the mold

Use the sling to slowly lift the mold above the installation position, and move carefully and slowly to avoid hitting surrounding objects; slide the injection molding machine guide column protection cover to the appropriate position, and the installer will hold the mold to stabilize and drop it to the appropriate position; install the positioning flange and protection ring to make it fit the injection port; close the sliding door, and start the mold adjustment button to enter the mold adjustment state.

3. Complete mold adjustment

Start the manual state of the injection molding machine, click the mold closing button to make the injection molding machine press the mold tightly; click the detection button to enter the password to enter the detection interface, and enter the number "1" after the switch mold. At this time, the switch mold spacing data is reset to zero, click the manual button to exit the detection state.

Install 8 mold blocks on both sides, install cooling water pipes at the same time, enter the detection interface again, and enter the number "1" after the switch mold to make the switch mold spacing data return to zero, and click the manual button to exit the detection state.

After completing the above operations, open and close the mold in the mold adjustment state to ensure that the mold is installed correctly, and then design parameters according to needs.

info-908-902